7 min readFor facility managers3 illustrations

Why one utility meter is not enough

Your utility bill tells you how much electricity the whole site used and, on many commercial rate plans, the highest demand during the billing period. It does not tell you which equipment caused it, whether the parkade fans ran all weekend, or why last January cost more than the one before.

Sub-metering adds meters on individual feeders, panels or pieces of equipment, so you can break total use down into parts. A dashboard turns that data into something people look at and act on.

Where sub-meters pay off

FIG 01Alberta Electrical
Single-line diagram of a utility meter feeding a distribution bus with four sub-metered feeders for HVAC, lighting, a tenant and EV charging, all reporting to a gateway. WHERE SUB-METERS GO UTILITY METER MAIN DISTRIBUTION M1M2M3M4 HVAC MCC LIGHTING TENANT A EV CHARGING DATA LINK GATEWAY / BAS METERS USE CTs ONEACH FEEDER TO DASHBOARD
Sub-meters on major feeders, each using current transformers, report through a gateway or BAS so energy use can be broken down by system or tenant.
  • Major mechanical loads: chillers, rooftop units, electric boilers, make-up air.
  • Lighting panels, to verify savings from an LED retrofit or controls.
  • Tenant spaces, for cost allocation or billing (see the rules below).
  • EV charging, which can add significant demand. Pair with EV load management.
  • Process equipment and compressed air in light industrial buildings.
  • Solar generation, to see production alongside consumption.

Start with the loads you can actually change. A meter on equipment that runs flat out all the time teaches you little.

How the meters work

FIG 02Alberta Electrical
Three phase conductors with a current transformer on each and fused voltage taps wired to a power meter that reports over Modbus. METER WIRING IN BRIEF ABC CURRENT TRANSFORMERS (CTs)AROUND EACH CONDUCTOR VOLTAGE TAPS (FUSED) POWERMETER MODBUS CT DIRECTION AND PHASE MATCHINGMUST BE RIGHT OR DATA IS WRONG
A sub-meter measures each phase's current with CTs and voltage through fused taps, then reports over a network protocol such as Modbus.

Most sub-meters measure current with current transformers (CTs) clipped or installed around each conductor and voltage through fused connections, then calculate energy, demand, power factor and more. They report over a network protocol such as Modbus or BACnet, or through pulse outputs, to a gateway, the BAS or a cloud service.

SafetyInstalled inside live equipment

CTs and voltage taps are installed inside panels and switchgear. This is work for a licensed electrician with the equipment de-energized where possible, following your site's safety procedures and with a permit where required.

Accuracy depends on the right CT sizes and correct installation. A CT on the wrong phase or installed backwards produces numbers that look plausible and are wrong, which is why a commissioning check against the main meter is worth doing.

Billing tenants: know the rules

Using sub-meter data to bill tenants for electricity is different from using it to manage energy. In Canada, electricity meters used for billing are regulated by Measurement Canada, which sets requirements for approved meters and verification. Allocation arrangements in leases are another matter again.

If you plan to bill from sub-meters, confirm the requirements before buying meters, not after. For internal management and cost tracking, ordinary energy meters are usually fine.

A dashboard people will use

Many energy dashboards are launched with enthusiasm and forgotten within months. The ones that last are simple and tied to decisions.

FIG 03Alberta Electrical
Line chart of building electrical demand over a day with a high overnight baseload highlighted and a midday peak marked. A WEEKDAY LOAD PROFILE: WHAT TO LOOK FOR kW OVERNIGHT BASELOAD: WHY SO HIGH? PEAK: WHAT STARTEDAT THE SAME TIME? START-UPRAMP 00:0006:0012:0018:00
A daily load profile shows the overnight baseload, the morning start-up and the daily peak, the three things most worth investigating on an energy dashboard.
  • Baseload: what runs when the building is empty? High overnight use is often the easiest saving.
  • Peak demand: when does it happen and what caused it? Staggering equipment starts can lower demand charges.
  • Comparisons: this week against last week, this January against last, adjusted for weather where possible.
  • Alerts: a message when a meter goes outside its normal range, rather than relying on someone to check.
  • One owner: a named person who reviews it on a regular schedule.
TipMeasure before you upgrade

Install meters before an LED retrofit, controls upgrade or equipment replacement. A few months of baseline data makes the savings provable afterward.

Planning a metering project

  1. Decide the questions first. Which decisions will the data support: tenant allocation, verifying a retrofit, finding waste, managing demand?
  2. Survey the electrical distribution. Up-to-date single-line drawings show where meters can go and how many are needed. Older buildings often need a site walk to confirm what feeds what.
  3. Choose meters and communication. Match accuracy class and protocol to the job and to the system that will collect the data.
  4. Plan the outages. Group installs to minimize shutdowns, and coordinate with tenants.
  5. Commission and verify. Check each meter's readings, phase rotation and CT direction, and compare the sum of sub-meters against the main meter.
  6. Assign an owner for the dashboard and a simple review routine.

Skipping the first step is the most common mistake. Meters installed without a clear purpose produce data nobody looks at.

Bringing it together

Sub-meters are most powerful when tied to the building automation system, so the same platform that shows the waste can schedule the fix. Our energy metering service designs and installs meters and dashboards, and our energy audits put the data to work. For smaller buildings, see building automation for small and mid-size buildings.

Common questions

Can we install sub-meters without shutting down power?

Some CTs are split-core and can be fitted around existing conductors, but working inside energized equipment carries real risk. Most installs are scheduled with a short planned outage. Your electrician will advise.

How accurate do sub-meters need to be?

For energy management, a good commercial-grade meter is usually enough. For tenant billing, Measurement Canada requirements apply and dictate which meters are acceptable.

Can we read our utility meter data directly?

Many utilities offer interval data through a customer portal, and some meters provide a pulse output. It is a good complement to sub-meters but will not break down usage by system.

Does sub-metering reduce our bill by itself?

No. Meters show where energy goes; savings come from acting on what they show, such as fixing schedules, reducing baseload and managing peaks.

About this guideGeneral information, not a site assessment

Codes and permit rules change and every building is different. For work on your system, talk to a licensed electrician and your local permit authority.